East Valley Parkway & Valley Center Road Improvements
Purpose
More Lanes Ahead...Drive Safely and Thanks For Your Patience.
This project takes the narrow and traffic-burdened East Valley Parkway thoroughfare to Valley Center and widens the road to help improve the flow of traffic. The end result will widen East Valley Parkway and Valley Center Road from Beven Drive to the Northern City limits, getting you where you need to be faster!
Schedule: September 2017 - November 2018
Features
- New six-lane extension of East Valley Parkway
- Undergrounding of existing overhead utilities
- Construction of a sound wall, landscaped medians, and sidewalks
- Bridge widening over the Escondido Creek
- Traffic signal modifications and the addition of 22 new LED streetlights
- Green street design with over 100 new trees
Project Update
January 2019 - Sixth Project Update
With the project nearing substantial completion, all travel lanes are now open to motorists. The new six-lane extension of East Valley Parkway is pictured in Figure 1.
Construction of the enhanced sound wall along the West side of the project is complete (Figure 2). Figure 3 highlights the sound wall pilasters faced with manufactured stone river rock. A combination of evergreen and flowering trees together with native and naturalized shrubs were planted along the parkway at the base of the sound wall. The landscape design is intended to serve as a transition between the existing streetscape at Eureka Ranch and the rural character of the Northern roadway.
The newly constructed entry monument sign (Figure 4) welcomes motorists traveling South into Escondido. The design of the sign matches the pilasters of the enhanced sound wall. The contractor will install an electrical service to power two ground-mounted light fixtures that will light the sign face. The stamped concrete medians are complete (Figure 5). The remaining median landscaping will be completed after the permanent replacement of the water main crossing of the median has been completed.
The contractor will continue to maintain the landscaping throughout the project for a 90-day maintenance period to achieve acceptable plan establishment.
-
Figure 2 - Enhanced Sound Wall along West side of project
-
Figure 3 - Sound Wall Pilasters
-
Figure 4 - Entry Monument Sign
-
Figure 5 - Stamped Concrete Median
-
Figure 1 - Widened Roadway
Previous Project Updates
Schedule of Work
| Project Items | Work Schedule | Scope of Work |
|---|---|---|
Item 1 | Mid-September | Mobilization - Clearing (east-side), installation of project information signs and erosion control devices. |
Item 2 | Mid-September - November 2017 | Construction of new roadway segment along Valley Center Road, North of Lake Wohlford Road |
Item 3 | Mid-September - December 2017 | Bridge widening begins across Escondido Creek. |
Item 4 | November - December 2017 | Construction of 8 foot sound wall. |
Item 5 | January - February 2018 | Utility Conversion |
Item 6 | March - April 2018 | Construction of concrete improvements on east-side of Valley Parkway |
Item 7 | April 2018 | Construction of new roadway section along east-side of East Valley Parkway and Valley Center Road |
Item 8 | Late - June 2018 | Masonry wall and concrete improvements. Grading for new roadway on the west-side of East Valley Parkway and Valley Center Road |
Item 9 | July - August 2018 | Installation of the remaining 15 LED street lights along project limits. Modification of the existing traffic signals at Beven Dr. and Lake Wohlford Road Activation of new traffic signal and new street lights. |
Item 10 | July - October 2018 | Planting of 100+ trees, shrubs, and drought tolerant plants. Includes installation of irrigation. |
Item 11 | Mid - July 2018 | Storm drain installation at intersection of Valley Center Road and Lake Wohlford Road Construction of two storm drain boxes and bio-filtration basin Number 4. |
| Item 12 | Late July | Installation of remaining water service laterals. |
| Item 13 | Late July | Placement of base material along west-side of Valley Center Road |
| Item 14 | August - October 2018 | Placement of asphalt roadway. |
| Item 15 | October - November 2018 | Landscape and Project Close-out |
In the News
Project Funding
Total Project Cost: $9.7 Million
Funding sources include an $800,000 contribution from the Rincon Band of Luiseño Indians, a $675,000 Highway Safety Improvement Program Grant, a $1.6 million Demonstration Grant, TransNet and Traffic Impact Fees.
Project Questions / Concerns
- Ricardo Cervantes, City of Escondido Field Engineering Inspector
- Geoff Bohne, L.B. Civil Vice President
Office: 760-294-0974
Email Geoff Bohne
Please note: To report non-emergency traffic safety issues outside of our normal working hours, and you feel this requires immediate attention, please contact our Non-Emergency Escondido Police Dispatch at 760-839-4722. When calling this number, please press "9" to speak with a live dispatch operator. Dispatch is available 24 hours a day, 7 days a week.
-
Ricardo Cervantes
Field Engineering InspectorPhone: 760-839-3853